From Saturday, June 15, to Sunday, June 16, Information Technology Services’ Network Engineering team will replace the Pullman DataCenter infrastructure. Please see the expected maintenance schedule and service impact:
June 15 from 8 a.m. – 5 p.m.
- Information Technology Building (ITB) and Sloan DataCenters will migrate to the new infrastructure.
- Impact: Services that rely on the DataCenter infrastructure may experience several small outages.
June 16 from 8 a.m. – 5 p.m.
- ITB 1010 will migrate to the new infrastructure.
- Impact: Services that rely on the infrastructure located in ITB 1010 will experience several small outages as cables are moved. Departments that have servers in ITB 1010 will be impacted.
To find more information regarding impacted buildings or services, along with answers to FAQs, please visit the Pullman DataCenter project page.